What is the result of increasing the value of the parameter ASM_POWER_LIMIT during a rebalance operation?()  
A: The ASM rebalance operation will likely consume fewer resources and complete in a shorter amount of time.
B: The ASM rebalance operation will consume fewer resources and complete in a longer amount of time.
C: The ASM rebalance operation will be parallelized and should complete in a shorter amount of time.
D: There is no ASM_POWER_LIMIT setting used in ASM.
E: None of the above.
出自:Oracle认证