In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?()
A:The safety valve escape piping should be disconnected from the valve body and a blank inserted
B:The boiler vent valves should be opened
C:All hand-hole/manhole covers should be tightened up as much as possible to preclude any leaks
D:All of the above
出自:海船船员证

完成拼图验证

按住下方滑块,将拼图拖到缺口处后松开。

拼图背景,将小拼图拖到缺口处
向右拖动滑块